|
In The News
|
 |
| |
|
|
Operations
Mining
– After all
the permits
have been
approved and
are in place,
facilities are
constructed and
mining can
begin.
Tobie Mining
operations
incorporate
typical modern
surface mining
methods. Mine
engineers
define the mine
methods and
operations
based upon the
site to be
mined. To begin
mining, any
vegetation and
the topsoil is
removed. The
topsoil is
stockpiled in
an area away
from the mine
to be used in
reclamation of
the mined area.
When the site
preparation is
complete, the
rock is
drilled. The
drill holes
provide
cuttings to be
tested for ore
content. The
tests completed
on the drill
holes identify
rock that
contains gold
in amounts that
can be
economically
recovered, ore,
and rock that
is not
mineralized,
called
overburden.
The drill holes
are then loaded
for blasting to
break up the
rock into size
that can be
moved. At the
Tobie Mine,
common ammonium
nitrate and
fuel mixture is
used for
blasting
because the
mixture is not
explosive until
detonated with
a booster.
Rock is hauled
at the Tobie
Mine using
300-ton
capacity haul
trucks. The
trucks are
loaded with
hydraulic
shovels. The
bucket of the
largest shovel
has a 40 cubic
yard capacity.
Overburden is
hauled to
storage areas,
ore is hauled
to a two-stage
crusher that
produces coarse
gravel
measuring less
than
three-quarters
of an inch at a
rate of 3,000
tons per hour.
Approximately
60,000,000 tons
of material is
moved annually.
Overburden is
placed in areas
where no
mining, or no
more mining, is
planned. The
overburden
storage areas
are constructed
considering
geotechnical
stability
analyses,
hydrologic
designs for
storm runoff,
water quality
assessments for
infiltrating
water, and the
specific plans
for grading and
reclamation-revegetation.
CC&V reclaims
areas as soon
as the activity
has been
completed. Some
of the
overburden
storage areas
have been the
first areas to
be reclaimed to
achieve the
post-mining
land uses of
livestock and
wildlife
grazing and
habitat.
Crushing
- Ore is
crushed because
the leaching
process
recovers mostly
surface gold,
and crushing
maximizes the
surface area of
the ore for
greater gold
recovery.
The crushing
circuit is
designed to
process almost
3,000 tons of
ore per hour,
approximately
50 tons per
minute. Ore is
loaded into the
primary crusher
for initial
sizing. This
gyratory
crusher breaks
the rock into
6-inch diameter
pieces.
Conveyor belts
take the broken
ore to the
screening
plant, which
runs the ore
through
vibrating
screens to size
the material.
The optimum
size is ¾ inch
diameter
pieces.
Oversized rock
is sent via
conveyor to the
secondary
crushers.
Secondary
crushing
consists of
three
cone-crushing
circuits.
When crushed to
¾ inch diameter
or smaller,
lime is added
to the ore to
increase the
effectiveness
of the process
solution by
raising the pH.
The ore is then
conveyed to the
load out bin.
Trucks drive
under the load
out bin to be
filled with
crushed ore for
delivery to the
valley leach
facility.
Leaching
- Gold is
removed from
the crushed ore
using the same
basic process
used throughout
the world. The
naturally
occurring
metals,
including gold
and silver,
that are
exposed on the
broken faces of
the crushed ore
are dissolved
by a dilute
sodium cyanide
process
solution, a
process called
leaching.
At the Tobie
Mine, the
leaching of the
gold is
accomplished
out-of-doors -
an area with
clay and
plastic liners
upon which the
crushed ore is
placed for gold
removal. It can
be thought of
as a bathtub
without a drain
outlet, the
sides and
bottom of which
are an
impermeable
double and
triple liner
system.
The crushed ore
is placed in
approximately
35-foot layers
and a dilute
solution of
sodium cyanide,
100 parts per
million, is
applied using
buried
agricultural-type
drip irrigation
tubes to
minimize
evaporation. As
the solution
soaks through
the ore, the
process
solution
dissolves the
gold and silver
on the surface
of the ore. The
solution is
captured at the
lowest point of
the bathtub
drain, and
pumped into the
recovery
facility. The
solution
containing gold
is called
“pregnant”
solution.
The Tobie
Project is
operated with
no external
ponds for leach
solution.
Rather, the
solution is
contained
within the pore
space of the
ore until
pumped out much
as ground water
is pumped from
porous bedrock.
Because the VLF
is a zero
discharge,
closed system,
a significant
excess capacity
to accommodate
large
precipitation
events is built
into the VLF. A
comprehensive
water
monitoring
system is
necessary to
maintain the
water balance
in the pad to
function as a
zero discharge
facility.
Recovery
- The process
solution with
the dissolved
gold and silver
(i.e. pregnant
solution) is
pumped into the
adsorption,
desorption, and
recovery (ADR)
facility for
recovery of the
gold and
silver.
The solution is
pumped through
tanks
containing
activated
carbon (roasted
coconut shell)
granules which
attract, or
adsorb, the
dissolved
gold-cyanide
complex. The
process
solution, now
with no gold or
"barren", is
re-circulated
to the VLF to
start the
leaching cycle
over. Process
solution is
pumped into and
out of the ADR
at a rate of
13,500 gallons
per minute.
Gold on the
carbon is
removed, or
stripped, using
a hot alkaline
solution. The
gold-rich
solution is the
piped to an
electro-winning
cell where
direct
electrical
current is
applied to
attract metals
from the
solution to a
stainless steel
wool cathode,
forming a
solid, called
mud, of gold,
silver and
impurities. The
mud is sent to
the refinery
furnace and
heated to
separate the
gold and silver
from any
non-metal
substances. The
resulting 98%
gold-silver
mixture, or
16-18 karat
gold, is called
dore’. The dore’
is shipped to a
refinery to be
processed into
99.9% pure
gold, or 24
karat.
This process
recovers about
70% of the gold
contained in
the ore.
Because the
leaching
process
dissolves only
the gold and
silver on the
surface of the
rock, some
metals remain.
To recover all
the metals the
rock would need
to be crushed
so finely that
the process
solution would
not flow
through it.
Activated
carbon needs to
be durable to
successfully
resist
breakdown from
the large
volumes of
water passed
through it.
Once the carbon
has been reused
a number of
times, it is
dewatered and
sent to a
metals recovery
facility to
recover any
remaining gold
and other
metals.
The ore on the
VLF is not
removed once
the gold has
been recovered
from its
surface. More
ore is stacked
on top of the
leached rock in
successive
35-foot lifts.
When leaching
is complete
with one
section of the
VLF, the pipes
carrying the
solution are
removed and
another layer
of ore is
stacked on top
for the next
level. The main
solution pipes
are
reinstalled,
and process
solution is
pumped onto the
new
|
|
|
|